Sunday, April 15, 2012

Asking for money before completion - Jan 2009

Email #7:  Asking for money before the project is finished.  Not how business should be done.

----- Original Message -----
From: <sales@arsmarine.com>
To: "Tom Blomme" <ztb@iw.net>
Sent: Friday, January 30, 2009 9:43 AM
Subject: Paint for boat.


> Tom,
>
> I had to strip the Paint/gel completely off the boat to get down to a good
> solid surface.
>
> The stuff that was on there was not gel coat, it was polyurethane paint
> 3" thick in some spots to help hide previous mistakes in body work. Due to
> this unforseen condition there is gonna be some additional labor cost's
> involved in the paint job.
>
> I'll need $3,500.00 to cover the cost of the Paint Materials.
>
>
> Here are some pictures of the deck.
>
>
>
> --
> Thank You
> George Pataki
> ARS Marine
> NEW Telephone #
> 1-(815)942-2600
> NEW Location--> Morris, IL.
>